Main Contractor: SIEMENS
Client: K Electric
Time Period: Aug 2018 – Oct 2018
Energisation Date: October 15, 2018
NEPCON executed Erection, Testing & Commissioning works of 132/11 KV AIS substations Hub Chowki, on
behalf of SIEMENS at TP-1000 Project. It is a 31.5/40MVA trafo-bay extension project in ring system
of Hub Chowki grid in which NEPCON achieved an extraordinary feat by installing all the HV equipment
during a single 48-hours long shutdown.