50MW Meridian Solar Plant, Sukkur
- Date: July 2022 – October 2023
- EPC Contractor: NEPCON
- Client: NTDC / CPPA / Scatec
Scope of Work: EPC – engineering, civil, installation, testing & commissioning, MEP works
About this Project
Adjacent to the HNDS plant, the Meridian Solar Project further strengthened NEPCON’s leadership in large-scale solar EPC works. The project introduced advanced pile technology for the first time in Pakistan.
Key Highlights & Achievements:
- Developed over 276 acres
- Parallel execution with HNDS and Helios projects
- Introduction of 4-meter solar pile technology
- In-house capability development for advanced ramming works
Related Services
Testing & Commissioning Services
NEPCON delivers comprehensive testing and commissioning services for high-voltage power infrastructure, ensuring assets are energized safely, perform as designed, and comply with utility and international standards.
Civil Works
NEPCON specializes in executing large-scale and technically complex civil works for power transmission, substations, and renewable energy projects.
Solar & Renewable Energy
Driving sustainable power through timely, bankable project delivery. Wind & Solar power plant civil and electro-mechanical works.
Contact Us
Karachi Office:
16 A/3 , Golf Course Road no. 4, DHA Phase 4, Karachi, Pakistan
Lahore Office:
20-A4 Punjab Govt Housing Society, Lahore, Pakistan
Email:
info@nepcon.pk