50MW Artistic II Wind Power Plant
- Date: June 2021 – March 2022
- EPC Contractor: Hydro China
- Client: NTDC / Hydro China
Scope of Work: Installation, testing & commissioning, fire alarm & firefighting, telecom, and building MEP works
About this Project
NEPCON successfully delivered erection, installation, testing, and commissioning services for the 50MW Artistic II Wind Power Plant as a back-to-back contractor to DESCON. The project contributed significant renewable capacity to the national grid within a record execution timeline.
Key Highlights & Achievements:
- Installation of RMU and electrical work for 20 wind turbines (2.5 MW each)
- Construction of 132/33kV AIS substation
- Integration with NTDC transmission network
- Completed within accelerated schedule
Related Services
Testing & Commissioning Services
NEPCON delivers comprehensive testing and commissioning services for high-voltage power infrastructure, ensuring assets are energized safely, perform as designed, and comply with utility and international standards.
Civil Works
NEPCON specializes in executing large-scale and technically complex civil works for power transmission, substations, and renewable energy projects.
Solar & Renewable Energy
Driving sustainable power through timely, bankable project delivery. Wind & Solar power plant civil and electro-mechanical works.