50MW Artistic II Wind Power Plant

  • Date: June 2021 – March 2022
  • EPC Contractor: Hydro China
  • Client: NTDC / Hydro China

    Scope of Work: Installation, testing & commissioning, fire alarm & firefighting, telecom, and building MEP works

About this Project

NEPCON successfully delivered erection, installation, testing, and commissioning services for the 50MW Artistic II Wind Power Plant as a back-to-back contractor to DESCON. The project contributed significant renewable capacity to the national grid within a record execution timeline.

    Key Highlights & Achievements:

    • Installation of RMU and electrical work for 20 wind turbines (2.5 MW each)
    • Construction of 132/33kV AIS substation
    • Integration with NTDC transmission network
    • Completed within accelerated schedule

    Related Services

    Testing & Commissioning Services

    NEPCON delivers comprehensive testing and commissioning services for high-voltage power infrastructure, ensuring assets are energized safely, perform as designed, and comply with utility and international standards.

    Civil Works

     

    NEPCON specializes in executing large-scale and technically complex civil works for power transmission, substations, and renewable energy projects.

     

    Solar & Renewable Energy

     

    Driving sustainable power through timely, bankable project delivery. Wind & Solar power plant civil and electro-mechanical works.

     