132kV Meridian AIS Substation, Sukkur Date: December 2022 – October 2023 EPC Contractor: SIEMENS Client: NTDC / CPPA / Scatec Scope of Work: Civil works, installation, testing & commissioning, MEP works About this Project Developed as part of the Scatec solar...
by admin | Feb 3, 2026
132kV HNDS AIS Substation, Sukkur Date: December 2022 – October 2023 EPC Contractor: SIEMENS Client: NTDC / CPPA / Scatec Scope of Work: Civil works, installation, testing & commissioning, MEP works About this Project Constructed to evacuate power from the 50MW...
by admin | Feb 2, 2026
132kV Helios AIS Substation, Sukkur Date: December 2022 – October 2023 EPC Contractor: SIEMENS Client: NTDC / CPPA / Scatec Scope of Work: Civil works, installation, testing & commissioning, MEP works About this Project Executed in parallel with HNDS and Meridian...
by admin | Feb 1, 2026
220kV GIS & 132kV AIS Dhabeji-1 Substation Date: March 2021 – February 2022 EPC Contractor: SIEMENS Client: K-Electric Scope of Work: Installation, Testing & Commissioning About this Project NEPCON executed erection, testing, and commissioning works to enhance...
by admin | Jan 31, 2026
220kV GIS KPC & 132kV GIS KTPS Substations (900MW BQPS-III) Date: March 2021 – February 2022 EPC Contractor: Harbin Electric International Co. Ltd. (HEI) Client: K-Electric Scope of Work: Installation, testing & commissioning, MEP, fire alarm &...