Main Contractor: SIEMENS
Client: K Electric
Time Period: Sep 2018 – April 2019
Energisation Date: April 28, 2019
NEPCON did Erection, Testing & Commissioning works of 132/11 KV GIS substations Queen’s Road (QRD), on behalf of SIEMENS at TP-1000 Project. It’s a two 31.5/40MVA trafo-bay and one-line bay extension. This grid is the most valuable grid in K-electric system which feed the US constellate and Bilawal house where NEPCON did all the extension works without any delay or tripping in the system and coupled two new GIS bays with the existing.