50 MW Artistic II Wind Power Project

wind tribune
wind tribune
EPC Contractor: Hydro China
Contractor: Descon
Client / End User: Artistic Milliners
Project Duration: Jun 2021 – Mar 2022
Scope of Work: Installation, Testing & Commissioning, Fire Alarm & Fighting System, Telecom, and Building MEP Works

Project Overview

NEPCON executed the Erection, Installation, Testing & Commissioning of this 50 MW wind project, adding renewable power to the NTDC network.

Scope included:

132/33 kV AIS substation
20 wind turbines (2.5 MW each)
Ring main units, transformers, inter-turbine cabling, 33 kV switchgear, power transformers, and 132 kV AIS yard